Project Management Professional (PMP) Exam Practice – Question1329

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?


A.
Finish-to-start planning
B. Rolling wave planning
C. Short term planning
D. Dependency determination

Correct Answer: B