Project Management Professional (PMP) Exam Practice – Question1335

After completion of one phase for a new product development project, the project manager realizes that the marketing departments acceptance criteria is missing.
What should the project manager do next?


A.
Initiate a change request to include the missing acceptance criteria.
B. Meet the marketing department to obtain their acceptance criteria.
C. Ask the sponsor to increase the budget to compensate for the missing acceptance criteria.
D. Negotiate with the marketing department to exclude their acceptance criteria.

Correct Answer: B