During the final stages of project execution, a dissatisfied customer requests that a feature be removed. The request is approved and will help complete the project on time.
What should the project manager do next?


A.
Review the changes with the project team.
B. Revise the communications management plan.
C. Reduce project resources to decrease costs.
D. Update the project scope baseline.

Correct Answer: A