Project Management Professional (PMP) Exam Practice – Question1337

During the closing of a complex project that includes several stakeholders, the project manager initiates a satisfaction evaluation. The contact information for one of the stakeholders is inaccurate.

What should the project manager do to obtain accurate stakeholder information?


A.
Contact the stakeholders individually.
B. Ask the sponsor for the updated stakeholder information.
C. Review the stakeholder engagement plan.
D. Refer to the stakeholder register.

Correct Answer: C