Project Management Professional (PMP) Exam Practice – Question1339

Collecting requirements is critical in project scope management as it becomes the foundation for the project's______________


A.
Scope management plan
B. WBS
C. Schedule
D. Scope change control system

Correct Answer: B

Explanation:

Explanation:
Collecting requirements provides the basis for defining project scope and product scope. It also involves determining, documenting, and managing stakeholder needs to meet project objectives. The requirements become the foundation for the WBS; moreover,
cost, schedule, and quality planning are built upon the requirements.