Project Management Professional (PMP) Exam Practice – Question1340

The project scope statement addresses and documents all the following items EXCEPT______________


A.
Project exclusions
B. The relationship between the deliverables and the business need
C. Product scope description
D. Project management methodology (PMM)

Correct Answer: B

Explanation:

Explanation:
The PMM is an organization-approved approach for project management that is used on every project. It is not part of the project scope statement, which describes the project scope, major deliverables, assumptions, and constraints. It describes the project’s
deliverables and the work required to complete them.