Project Management Professional (PMP) Exam Practice – Question1341

The first step in collecting requirements on any project, large or small, is to______________


A.
Talk with the project stakeholders through interviews
B. Review the scope management plan
C. Conduct facilitated workshops with stakeholders
D. Prepare a requirements document template that you and your team can use throughout the collect requirements process

Correct Answer: B

Explanation:

Explanation:
The scope management plan is reviewed first as it provides clarity as to how the project team will determine which requirements need to be collected on the project.