You want to structure your project so that each project team member has a discrete work package to perform. The work package is a______________


A.
Deliverable at the lowest level of the WBS
B. Task with a unique identifier
C. Required level of reporting
D. Task that can be assigned to more than one organizational unit

Correct Answer: A

Explanation:

Explanation:
A work package is the lowest or smallest unit of work division in a project or WBS. The work package can be scheduled, cost estimated, monitored, and controlled.