Project Management Professional (PMP) Exam Practice – Question1345
Change is inevitable on projects. Uncontrolled changes are often referred to as______________
A. Rework B. Scope creep C. Configuration items D. Emergency changes
Correct Answer: B
Explanation:
Explanation:
Project scope creep is typically the result of uncontrolled changes. Scope control works to control the impact of any project scope changes.