In scope control it is important to determine the cause of any unacceptable variance relative to the scope baseline. This can be done through______________
A. Root cause analysis
B. Control charts
C. Inspections
D. Project performance measurements
A. Root cause analysis
B. Control charts
C. Inspections
D. Project performance measurements