Project Management Professional (PMP) Exam Practice – Question1347

In scope control it is important to determine the cause of any unacceptable variance relative to the scope baseline. This can be done through______________


A.
Root cause analysis
B. Control charts
C. Inspections
D. Project performance measurements

Correct Answer: D

Explanation:

Explanation:
Variance analysis is a tool and technique for control scope. Project performance measurements are used to assess the magnitude of variance, to determine the cause of the variance, and to decide whether corrective or preventive action is required.