Project Management Professional (PMP) Exam Practice – Question1350

Assume that you are a major subcontractor doing work for a prime contractor on a major project. Your change control system should______________


A.
Be identical to that of the prime contractor
B. Follow the rigor of international configuration management standards
C. Comply with relevant contractual provisions
D. Only consider approved change requests

Correct Answer: C

Explanation:

Explanation:
In addition to complying with any relevant contractual provisions, scope change control must be integrated with the project’s overall change control system and with any systems in place to control project and product scope.