Project Management Professional (PMP) Exam Practice – Question1353

Any step recommended to bring expected future performance in line with the project management plan is called______________


A.
Performance evaluation
B. Corrective action
C. Preventive action
D. Defect repair

Correct Answer: B

Explanation:

Explanation:
Recommended corrective action is an output from control scope. In addition to bringing expected future performance in line with the project management plan, it also serves to bring expected future performance in line with the project scope statement.