Project Management Professional (PMP) Exam Practice – Question1355

Updates of organizational process assets that are an output of control scope include all the following EXCEPT______________


A.
Causes of variations
B. Lessons learned
C. Work authorization system
D. Reasons certain corrective actions were chosen

Correct Answer: C

Explanation:

Explanation:
The work authorization system is not used in control scope. The others are examples of organizational process assets that may require update as a result of scope control.