Project Management Professional (PMP) Exam Practice – Question1356

Work performance information includes all the following EXCEPT______________


A.
Started deliverables
B. Costs authorized and incurred
C. Progress of deliverables
D. Completed deliverables

Correct Answer: B

Explanation:

Explanation:
Work performance information is an output of validate scope. It emphasizes deliverables whether or not they have started, their progress, and ones that have finished or have been accepted.