Your customer signed off on the requirements document and scope statement of your video game project last month. Today she stated she would like to make it an interactive game that can be played on a television and on a computer. This represents a
requested scope change that, at a minimum______________
A. Should be reviewed according to the perform integrated change control process
B. Results in a change to all project baselines
C. Requires adjustments to cost, time, quality, and other objectives
D. Results in a lesson learned