Project Management Professional (PMP) Exam Practice – Question1361

Modifications may be needed to the WBS and WBS dictionary because of approved change requests, which shows that______________


A.
Replanning is an output of control scope
B. Scope creep is common on projects
C. Rebaselining will be necessary
D. Variance is relative to the scope baseline

Correct Answer: D

Explanation:

Explanation:
Approved change requests will most likely impact and cause updates to the WBS, WBS dictionary, and project scope statement. In other words, they will cause variance to the scope baseline.