You and your team are documenting requirements on you project to control fatigue as people need to work more hours to keep up with the competition. You decided to set up components for the requirements on your project. Acceptance criteria are an example
of______________


A.
Stakeholder requirements
B. Transition requirements
C. Project requirements
D. Business requirements

Correct Answer: C

Explanation:

Explanation:
Various components of requirements documentation can be used. Examples are: business requirements, stakeholder requirements, solution requirements, project requirements, and requirements assumptions, dependencies, and constraints. Project
requirements consist of acceptance criteria and levels of service performance, safety, and compliance.