Project Management Professional (PMP) Exam Practice – Question1365

The project scope statement is important in scope control because it______________


A.
Is a critical component of the scope baseline
B. Provides information on project performance
C. Alerts the project team to issues that may cause problems in the future
D. Is expected to change throughout the project

Correct Answer: A

Explanation:

Explanation:
The project scope statement, along with the WBS and WBS dictionary, is a key input to scope control.