Project Management Professional (PMP) Exam Practice – Question1366

The product scope description is documented as part of the project's scope statement. It is important to include it because it______________


A.
Facilitates the project acceptance process
B. Describes specific constraints associated with the project
C. Progressively elaborates characteristics
D. Shows various alternatives considered

Correct Answer: C

Explanation:

Explanation:
The project scope statement describes the deliverables and the work required to create them. It also provides a common understanding of the scope among stakeholders. The product scope statement is a key component as it progressively elaborates the
characteristics of the product, service, or result in the project charter and requirements documentation.