Project Management Professional (PMP) Exam Practice – Question1368

You are establishing a PMO that will have a project management information system that will be an online repository of all program data. You will collect descriptions of all work components for each project under the PMO's jurisdiction. This information will form
an integral part of the______________


A.
Chart of accounts
B. WBS dictionary
C. WBS structure template
D. Earned value management reports

Correct Answer: B

Explanation:

Explanation:
The WBS dictionary typically includes a code of accounts identifier, a statement of work, responsible organization, a list of schedule milestones, associated schedule activities, required resources, cost estimates, quality requirements, acceptance criteria, technical
references, and agreement information.