Project Management Professional (PMP) Exam Practice – Question1370

Diagram:

What is the float for Activity G?


A.
-2
B. 0
C. 1
D. 4

Correct Answer: C

Explanation:

Explanation:
Float = (late finish -early finish) or
(Late start -early start)
Activity G LF = 12 (12 -11) = (1)
EF = 11
LS = 7 (7 -6) = (1)
ES = 6