Project Management Professional (PMP) Exam Practice – Question1370 Diagram: What is the float for Activity G? A. -2 B. 0 C. 1 D. 4 Show Answer Hide Answer Correct Answer: C Explanation: Explanation: Float = (late finish -early finish) or (Late start -early start) Activity G LF = 12 (12 -11) = (1) EF = 11 LS = 7 (7 -6) = (1) ES = 6 Post navigation Project Management Professional (PMP) Exam Practice – Question1369Project Management Professional (PMP) Exam Practice – Question1371