Project Management Professional (PMP) Exam Practice – Question1371

Diagram:

If a project planner imposes a finish time of 14 on the project with no change in the start date or activity durations, what is the total float of Activity E?


A.
-1
B. 0
C. 2

D. Cannot be determined

Correct Answer: A

Explanation:

Explanation:
The imposed finish date becomes the late finish for Activity I. The late dates for each activity need to be recalculated. The dates for Activity E become______________
ES = 10
EF = 13
LS = 9LF = 12
Total float = LS -ES or 9 -10 = (-1) or
LS -EF or 12 -13 = (-1)