Project Management Professional (PMP) Exam Practice – Question1372

Diagram:

If the imposed finish time in question 3 above is removed and reset to 16 and the duration of Activity H is changed to 3, what is the late finish for Activity G?


A.
-11
B. 11
C. -13
D. 13

Correct Answer: B

Explanation:

Explanation:
The late dates for all activities need to be recalculated given the changed duration. Activity G’s revised late dates are______________
LF = 11
LS = 6