You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. The titanium pipe must be resting in the ground a total of 10 days before connectors can be
installed. In this example, the 10-day period is defined as______________
A. Lag
B. Lead
C. Float
D. Slack
installed. In this example, the 10-day period is defined as______________
A. Lag
B. Lead
C. Float
D. Slack