Project Management Professional (PMP) Exam Practice – Question1374

You are managing a construction project for a new city water system. The contract requires you to use special titanium piping equipment that is guaranteed not to corrode. The titanium pipe must be resting in the ground a total of 10 days before connectors can be
installed. In this example, the 10-day period is defined as______________


A.
Lag
B. Lead
C. Float
D. Slack

Correct Answer: A

Explanation:

Explanation:
For example, in a finish-to-start dependency with a 20-day lag, the successor activity cannot start until 20 days after the predecessor has finished.