Project Management Professional (PMP) Exam Practice – Question1375

Of the following tools and techniques, which one is NOT used for schedule control?


A.
Fast tracking
B. What-if scenario analysis
C. Three-point estimates
D. Adjusting leads and lags

Correct Answer: C

Explanation:

Explanation:
Three-point estimates are used to determine the estimates that go into the schedule. [Planning and Monitoring and Controlling]