Project Management Professional (PMP) Exam Practice – Question1376

You are planning to conduct the team-building portion of your new project management training curriculum out-of-doors in the local park. You are limited to scheduling the course at certain times of the year, and the best time for the course to begin is mid-July.
One of the more common date constraints to use as you develop the project schedule is______________


A.
"Start no earlier than"
B. "Finish no earlier than"
C. "Fixed late start"
D. "Fixed early finish"

Correct Answer: A

Explanation:

Explanation:
Imposed dates on schedule activity starts of finishes can be used to restrict the start of finish to occur either no earlier than a specified date or no later than a specified date. Although all four date constraints typically are available in project management software,
“start no earlier than” and “finish no later than” constraints are more commonly used.