You are planning to conduct the team-building portion of your new project management training curriculum out-of-doors in the local park. You are limited to scheduling the course at certain times of the year, and the best time for the course to begin is mid-July.
One of the more common date constraints to use as you develop the project schedule is______________
A. "Start no earlier than"
B. "Finish no earlier than"
C. "Fixed late start"
D. "Fixed early finish"