Project schedule development is an iterative process. If the start and finish dates are not realistic, the project probably will not finish as planned. You are working with your team to define how to manage schedule changes. You documented your decisions in which
of the following?
A. Schedule change control procedures
B. Schedule management plan
C. Schedule risk plan
D. Service-level agreement
of the following?
A. Schedule change control procedures
B. Schedule management plan
C. Schedule risk plan
D. Service-level agreement