Project Management Professional (PMP) Exam Practice – Question1377

Project schedule development is an iterative process. If the start and finish dates are not realistic, the project probably will not finish as planned. You are working with your team to define how to manage schedule changes. You documented your decisions in which
of the following?


A.
Schedule change control procedures
B. Schedule management plan
C. Schedule risk plan
D. Service-level agreement

Correct Answer: B

Explanation:

Explanation:
The schedule management plan is part of the overall project management plan and defines, among other things, how schedule changes will be managed. Whether it is formal or informal, highly detailed or broadly framed, it generally is based on specific project
needs.