If, when developing your project schedule, you want to define a distribution of probable results for each schedule activity and use that distribution to calculate another distribution of probable results for the total project, the most common technique to use
is______________
A. PERT
B. Monte Carlo analysis
C. Linear programming
D. Concurrent engineering