Project Management Professional (PMP) Exam Practice – Question1380

Your customer wants the project to be completed six months earlier than planned. You believe you can meet this target by overlapping project activities. The approach you plan to use is known as______________


A.
Critical chain
B. Fast tracking
C. Leveling
D. Crashing

Correct Answer: B

Explanation:

Explanation:
Fast tracking is a way to accelerate the project schedule.