Project Management Professional (PMP) Exam Practice – Question1384

Working with your team to provide the basis for measuring and reporting schedule progress, you agree to use the______________


A.
Schedule management plan
B. Network diagram
C. Project schedule
D. Technical baseline

Correct Answer: C

Explanation:

Explanation:
The approved project schedule is a key input to schedule control. It is the schedule baseline, as it is the approved version of a schedule model, and it provides the basis for measuring and reporting schedule performance.