Working with your team to provide the basis for measuring and reporting schedule progress, you agree to use the______________
A. Schedule management plan
B. Network diagram
C. Project schedule
D. Technical baseline
A. Schedule management plan
B. Network diagram
C. Project schedule
D. Technical baseline