Project Management Professional (PMP) Exam Practice – Question1385

Your approved project schedule was based on resource leveling because of a scarcity of resources. Management has now mandated that the project be completed as soon as possible. Which of the following methods will you use to recalculate the schedule?


A.
Resource manipulation
B. Reverse resource allocation
C. Critical chain scheduling
D. Resource reallocation

Correct Answer: D

Explanation:

Explanation:
While resource leveling will often result in a project duration that is longer than the preliminary schedule as the original critical path probably will change and increase, it can also be used to get a schedule back on track by reassigning activities from noncritical to
critical path activities.