Your approved project schedule was based on resource leveling because of a scarcity of resources. Management has now mandated that the project be completed as soon as possible. Which of the following methods will you use to recalculate the schedule?
A. Resource manipulation
B. Reverse resource allocation
C. Critical chain scheduling
D. Resource reallocation