Project Management Professional (PMP) Exam Practice – Question1386

Review the following network diagram and table.

Of the various activities, which ones would you crash and in what order?


A.
A, C, E, andF
B. A, B, D, andF
C. A, B, E, andF
D. C, A, F, andG

Correct Answer: D

Explanation:

Explanation:
First, it is necessary to determine the critical path, which is A, C, F, and G. To determine the lowest weekly crashing cost, start with C at $1,500 per week. The next activity is A, followed by F and G.