You are remodeling your kitchen and decide to prepare a network diagram for this project. Your appliances must be purchased and available for installation by the time the cabinets are completed. In this example, these relationships are______________
A. Start-to-finish
B. Finish-to-start
C. Start-to-start
D. Finish-to-finish
A. Start-to-finish
B. Finish-to-start
C. Start-to-start
D. Finish-to-finish