Project Management Professional (PMP) Exam Practice – Question1387

You are remodeling your kitchen and decide to prepare a network diagram for this project. Your appliances must be purchased and available for installation by the time the cabinets are completed. In this example, these relationships are______________


A.
Start-to-finish
B. Finish-to-start
C. Start-to-start
D. Finish-to-finish

Correct Answer: D

Explanation:

Explanation:
The completion of the work of the successor activity depends upon the completion of the work of the predecessor activity.