When sequencing project activities in the schedule, all the following are true EXCEPT______________
A. There may be scheduled dates for specific milestones
B. Every activity is connected to at least one predecessor and at least one successor
C. Lead or lag time may be required
D. Necessary sequencing of events may be described by the activity attributes