Project Management Professional (PMP) Exam Practice – Question1389

When sequencing project activities in the schedule, all the following are true EXCEPT______________


A.
There may be scheduled dates for specific milestones
B. Every activity is connected to at least one predecessor and at least one successor
C. Lead or lag time may be required
D. Necessary sequencing of events may be described by the activity attributes

Correct Answer: B

Explanation:

Explanation:
The sequence activity process involves identifying and documenting relationships among the project activities. However, the last activity or milestone are not connected to at least one successor.