Project Management Professional (PMP) Exam Practice – Question1391

Various tools and techniques are available to sequence activities, and several factors can help to determine which tool or technique to select. When a project manager decides to include sub-networks or a fragment network as part of his or her scheduling
technique, what does this decision say about the project?


A.
The work is unique requiring special network diagrams at various stages.
B. Software that manages resources is available over an existing electronic network.
C. Several identical or nearly identical series of activities are repeated throughout the project.

D. Multiple critical paths exist in the project.

Correct Answer: C

Explanation:

Explanation:
When identical network descriptions are repeated throughout a project, templates of those activities can be developed. If those series of tasks are repeated several times, the template can be updated several times. Software can be used with the templates to
facilitate documenting and adapting them for future use. The sub-network or fragment tends to represent a sub-project or a work package and is often used to illustrate or study some potential or proposed schedule condition, such as a change in preferential
schedule logic or the scope of the project.