To meet regulatory requirements, you need to crash your project schedule. Your first step is to compute______________
A. The cost and time slope for each critical activity that can be expedited
B. The cost of additional resources to be added to the project's critical path
C. The time saved in the overall schedule when tasks are expedited on the critical path
D. Three probabilistic time estimates of PERT for each critical path activity
A. The cost and time slope for each critical activity that can be expedited
B. The cost of additional resources to be added to the project's critical path
C. The time saved in the overall schedule when tasks are expedited on the critical path
D. Three probabilistic time estimates of PERT for each critical path activity