Project Management Professional (PMP) Exam Practice – Question1393

Which one of the following is a key input to the define activities process?


A.
Project management plan
B. Project scope statement
C. Project scope baseline
D. Project charter

Correct Answer: C

Explanation:

Explanation:
The scope baseline made up of the scope statement, WBS, and WBS dictionary is a key input to the define activities process and are used to develop the activity list that subsequently will help to create the schedule.