Project Management Professional (PMP) Exam Practice – Question1394

Unlike bar charts, milestone charts show______________


A.
Scheduled start or completion of major deliverables and key external interfaces
B. Activity start and end dates of critical tasks
C. Expected durations of the critical path
D. Dependencies between complementary projects

Correct Answer: A

Explanation:

Explanation:
Scheduled start or completion of major deliverables and key external interfaces Milestones are singular points in time, such as the start or completion of a significant activity or group of activities.