Project Management Professional (PMP) Exam Practice – Question1395

Project managers should pay attention to critical and subcritical activities when evaluating project time performance. One way to do this is to analyze 10 sub critical paths in order of ascending float. This approach is part of______________


A.
Variance analysis

B. Simulation
C. Earned value management
D. Trend analysis

Correct Answer: A

Explanation:

Explanation:
Performance of variance analysis during the schedule monitoring process is a key element of time control. Float variance is an essential planning component for evaluating project time performance.