Project Management Professional (PMP) Exam Practice – Question1397

In project development, schedule information such as who will perform the work, where the work will be performed, activity type, and WBS classification are examples of______________


A.
Activity attributes
B. Constraints
C. Data in the WBS repository
D. Refinements

Correct Answer: A

Explanation:

Explanation:
Identifying activity attributes is helpful for further selection and sorting of planned activities. They are used for schedule development and for report formatting purposes.