Project Management Professional (PMP) Exam Practice – Question1398

Which of the following is a key input to define activities?


A.
Project management plan
B. Project scope management plan
C. Schedule management plan
D. Project management software

Correct Answer: C

Explanation:

Explanation:
While there are a number of inputs to define activities, the schedule management plan is a key input. It shows the level of detail necessary to manage the work.