Project Management Professional (PMP) Exam Practice – Question1400

Several types of float are found in project networks. Float that is used by a particular activity and does NOT affect the float in later activities is called______________


A.
Extra float
B. Free float
C. Total float
D. Expected float

Correct Answer: B

Explanation:

Explanation:
Free float is defined as the amount of time an activity can be delayed without delaying the early start of any immediately succeeding activities.