You are managing a new technology project designed to improve the removal of hazardous waste from your city. You are in the planning phase of this project and have prepared your network diagram. Your next step is to______________


A.
Describe any unusual sequencing in the network
B. State the number resources required to complete each activity
C. Establish a project calendar and link it to individual resource calendar
D. Determine which schedule compression technique is the most appropriate, because your customer requests that the project be completed as soon as possible

Correct Answer: A

Explanation:

Explanation:
A summary narrative can accompany the schedule network diagram and describe the approach used to sequence the activities in the network. This narrative also should describe any unusual sequences in the network.