You are managing a project to redesign a retail store layout to improve customer throughput and efficiency. Much project work must be done on site and will require the active participation of store employees who are lifelong members of a powerful union with a
reputation for labor unrest. One important component of your schedule must be______________
A. A resource capabilities matrix
B. Buffers and reserves
C. A resource calendar
D. A resource histogram