Project Management Professional (PMP) Exam Practice – Question1406

You are managing a project to redesign a retail store layout to improve customer throughput and efficiency. Much project work must be done on site and will require the active participation of store employees who are lifelong members of a powerful union with a
reputation for labor unrest. One important component of your schedule must be______________


A.
A resource capabilities matrix
B. Buffers and reserves
C. A resource calendar
D. A resource histogram

Correct Answer: C

Explanation:

Explanation:
Project and resource calendars identify periods when work is allowed. Project calendars affect all resources. Resource calendars affect a specific resource or a resource category, such as a labor contract that requires certain workers to work on certain days of
the week.