You have now prepared your cost management plan so now you are preparing your project's cost estimate. You decided to use analogous estimating. Which of the following is NOT characteristic of analogous estimating?
A. Supports top-down estimating
B. Is a form of expert judgment
C. Has an accuracy rate of 10% of actual costs
D. Involves using the cost of a previous, similar project as the basis for estimating current project cost
A. Supports top-down estimating
B. Is a form of expert judgment
C. Has an accuracy rate of 10% of actual costs
D. Involves using the cost of a previous, similar project as the basis for estimating current project cost