Project Management Professional (PMP) Exam Practice – Question1414

All the following are outputs of the estimate cost process EXCEPT______________


A.
Activity cost estimates
B. Basis of estimates
C. Documented constraints
D. Cost baseline

Correct Answer: D

Explanation:

Explanation:
Cost baseline is an output from the determine budget process.