Project Management Professional (PMP) Exam Practice – Question1418

Management has grown weary of the many surprises, mostly negative, that occur on your projects. In an effort to provide stakeholders with an effective performance metric, you will use the to-complete performance index (TCPI). Its purpose is to______________


A.
Determine the schedule and cost performance needed to complete the remaining work within management's financial goal for the project
B. Determine the cost performance needed to complete the remaining work within management's financial goal for the project
C. Predict final project costs
D. Predict final project schedule and costs

Correct Answer: B

Explanation:

Explanation:
Determine the cost performance needed to complete the remaining work within management’s financial goal for the project The TCPI takes the value of work remaining and divides it by the value of funds remaining to obtain the cost performance factor needed to
complete all remaining work according to a financial goal set by management.