If operations on a work package were estimated to cost $1,500 and finish today but, instead, have cost $1,350 and are only two-thirds complete, the cost variance is______________
A. $150
B. -$150
C. -$350
D. -$500
A. $150
B. -$150
C. -$350
D. -$500