Project Management Professional (PMP) Exam Practice – Question1424

If you want to calculate the ETC based on your expectations that similar variances to those noted to date will not occur, you should use which of the following formulas?


A.
ETC =BAC -EV
B. ETC = (BAC -EV)/CPI
C. ETC =AC +EAC
D. ETC =AC +BAC -EV

Correct Answer: A

Explanation:

Explanation:
This formula assumes that the estimate to complete is based on the same cost efficiency level.