Project Management Professional (PMP) Exam Practice – Question1426

Your approved cost baseline has changed because of a major scope change on your project.
Your next step should be to______________


A.
Estimate the magnitude of the scope change
B. Issue a change request
C. Document lessons learned
D. Execute the approved scope change

Correct Answer: B

Explanation:

Explanation:
Before a revised cost baseline leading to a budget update can be prepared, it is necessary to issue a change request, which may include preventive or corrective action. These change requests then are reviewed and processed through the Perform Integrated
Change Control process.